Home > Photo Gallery > Mianyang Special Education School for the Disabled Construction Progress
Mianyang Special Education School for the Disabled Construction Progress

Wood Frame Work
7-8 - Students Dorm and Classroom Building Seen from West
7-8 - Students Dorm and Classroom Building Seen from West
 
7-8 Classroom Building Almost Complete
7-8 Classroom Building Almost Complete
 
7-6 Tower is Ready for Uninstalling Scaffolding
7-6 Tower is Ready for Uninstalling Scaffolding
 
7-5 Painting the Siding
7-5 Painting the Siding
 
7-4 Installing Facia on Classroom Building
7-4 Installing Facia on Classroom Building
 
7-2 Backside of Teachers Dorm
7-2 Backside of Teachers Dorm
 
6-6 Administration Building seen Between two Towers
6-6 Administration Building seen Between two Towers
 
6-4 Admin Second Floor Hall Ceiling Completed
6-4 Admin Second Floor Hall Ceiling Completed
 
6-1 Starting the SBS Sheeting
6-1 Starting the SBS Sheeting
 
6-1 Electricians Keeping Piping Parallel
6-1 Electricians Keeping Piping Parallel
 
5-22 Trusses Fabricated for Kitchen
5-22 Trusses Fabricated for Kitchen
 
5-18 Students Dorm
5-18 Students Dorm
 
5-16 Teachers Dorm
5-16 Teachers Dorm
 
5-16 Framing Cafeteria Walls
5-16 Framing Cafeteria Walls
 
5-12 Nailing Treads and Risers
5-12 Nailing Treads and Risers
 
5-10 Forming Walls Against the Tower of the Classroom
5-10 Forming Walls Against the Tower of the Classroom
 
5-10 Dorm Building Seen from the South
5-10 Dorm Building Seen from the South
 
5-8 FII China Staff Working with Fire Foreman on Piping
5-8 FII China Staff Working with Fire Foreman on Piping
 
4-6 Installing Classroom Ceiling
4-6 Installing Classroom Ceiling
 
4-6 Installing Sheathing for South Classroom Trusses
4-6 Installing Sheathing for South Classroom Trusses
 
4-5 Tapered Truss Tails
4-5 Tapered Truss Tails
 
4-3 Truss Strapping Finished in Teachers Dorm
4-3 Truss Strapping Finished in Teachers Dorm
 
4-3 Framing North Classroom Hall Walls
4-3 Framing North Classroom Hall Walls
 
4-2 North Classroom Interior Walls Going Up
4-2 North Classroom Interior Walls Going Up
 
4-1 North CLassroom framing Dorm Front View
4-1 North CLassroom framing Dorm Front View
 
4-1 First Gable Walls go up on the North Classroom
4-1 First Gable Walls go up on the North Classroom
 
4-1 Installing Shear and OSB for Classrrom
4-1 Installing Shear and OSB for Classrrom
 
3-30 South Classroom Framing
3-30 South Classroom Framing
 
3-30 North Classroom Floor Work
3-30 North Classroom Floor Work
 
2-24 Roof Sheathing Seen from Beneath
2-24 Roof Sheathing Seen from Beneath
 
2-23 Hall Framing in the Student Dorm
2-23 Hall Framing in the Student Dorm
 
2-1 Installing Exterior Sheathing on the Student Dorm
2-1 Installing Exterior Sheathing on the Student Dorm
 
1-29 2X10 Accents on Truss Tails are added
1-29 2X10 Accents on Truss Tails are added
 
1-28 Scaffolding is up on the Dorm
1-28 Scaffolding is up on the Dorm
 
1-28 Double LVL in Rim Position Over the Exterior Walls
1-28 Double LVL in Rim Position Over the Exterior Walls
 
1-26 Trusses Ready for the Detail Tails to be Added
1-26 Trusses Ready for the Detail Tails to be Added
 
1-26 Scaffolding Starts up on the Wood Frame Structures
1-26 Scaffolding Starts up on the Wood Frame Structures
 
1-26 Only a Few Trusses left to Install on the Students Dorm
1-26 Only a Few Trusses left to Install on the Students Dorm
 
1-26 Gable end of the Student Dorm
1-26 Gable end of the Student Dorm
 
1-26 Framing the Clearstory above the Teachers Dorm Hallway
1-26 Framing the Clearstory above the Teachers Dorm Hallway
 
1-21 Both Clearstory Vent Walls are Standing in Student Dorm
1-21 Both Clearstory Vent Walls are Standing in Student Dorm
 
1-20 Student Dorm Clearstory Vent Wall Standing
1-20 Student Dorm Clearstory Vent Wall Standing
 
1-19 Teachers Dorm Walls Taking Shape
1-19 Teachers Dorm Walls Taking Shape
 
1-19 Maually Sharpening Hand Saw During Power Shortage
1-19 Maually Sharpening Hand Saw During Power Shortage
 
1-18 Teachers Dorm Interior Walls being Framed
1-18 Teachers Dorm Interior Walls being Framed
 
1-18 Students Dorm Hallway on Second Floor
1-18 Students Dorm Hallway on Second Floor
 
1-18 OSB Floor Completed on Teachers Dorm and Sill Plates Marked
1-18 OSB Floor Completed on Teachers Dorm and Sill Plates Marked
 
1-15 Student Dorm Walls Produced
1-15 Student Dorm Walls Produced
 
1-15 Rolling the Joists to the Teachers Dorm
1-15 Rolling the Joists to the Teachers Dorm
 
1-15 Students Dorm Hall Walls Finished
1-15 Students Dorm Hall Walls Finished
 
1-14 Wall Framing Starts on the Second Floor
1-14 Wall Framing Starts on the Second Floor
 
1-14 East Dorm Plating is being Finished
1-14 East Dorm Plating is being Finished
 
1-13 Snapping Lines for Walls on the Second Floor
1-13 Snapping Lines for Walls on the Second Floor
 
1-12 OSB Flooring
1-12 OSB Flooring
 
1-12 Framing in the Teachers Dorm
1-12 Framing in the Teachers Dorm
 
1-12 Piping Installation in the Joists
1-12 Piping Installation in the Joists
 
1-12 Backing for Edge Nailing put in the Dropped Floors
1-12 Backing for Edge Nailing put in the Dropped Floors
 
1-10 West Dorm Seen from Tower
1-10 West Dorm Seen from Tower
 
1-10 West Dorm Framing
1-10 West Dorm Framing
 
1-10 East Dorm Seen from Tower
1-10 East Dorm Seen from Tower
 
1-10 East Dorm Framing
1-10 East Dorm Framing
 
1-4 Dorm Seen from Property Line
1-4 Dorm Seen from Property Line
 
1-4 Precut and Nailed Headers Ready for Second Floor Work
1-4 Precut and Nailed Headers Ready for Second Floor Work
 
1-3 Pressing Process
1-3 Pressing Process
 
1-3 Precut Truss Parts Stack-up
1-3 Precut Truss Parts Stack-up
 
1-3 Interior Shear Finished
1-3 Interior Shear Finished
 
1-3 Corridor Wall Braced and Ready
1-3 Corridor Wall Braced and Ready
 
1-1 Cutting OSB for Shear Walls
1-1 Cutting OSB for Shear Walls
 
1-1 Top Plates On
1-1 Top Plates On
 
1-1 First Truss is Made
1-1 First Truss is Made
 
12-30 Interior Framing Starting to Sow
12-30 Interior Framing Starting to Sow
 
12-28 Walls Coming Together
12-28 Walls Coming Together
 
12-28 Exterior Walls Framed On-site
12-28 Exterior Walls Framed On-site
 
12-26 First Interior Wall Erected
12-26 First Interior Wall Erected
 
12-26 First Wall Assembled on Site
12-26 First Wall Assembled on Site
 
12-26 Men Working on the Lumber
12-26 Men Working on the Lumber
 
12-25 Shim Work set to a String Line
12-25 Shim Work set to a String Line
 
12-24 Sil Gasket on First
12-24 Sil Gasket on First
 
12-24 Plate Starts Down
12-24 Plate Starts Down
 
Lumber Arrives on Site
1-27 Treated Materials Arrive
1-27 Treated Materials Arrive
 
12-16 Foundation Work Progress as Lumber Arrives
12-16 Foundation Work Progress as Lumber Arrives
 
12-16 Second Truck Load
12-16 Second Truck Load
 
12-16 Canfor Lumber
12-16 Canfor Lumber
 
12-16 Dunkley Lumber
12-16 Dunkley Lumber
 
12-16 Tolko Lumber
12-16 Tolko Lumber
 
12-15 Lumber Arrives on Site at 3:30AM
12-15 Lumber Arrives on Site at 3:30AM
 
12-15 Second Truck Loaded with 2X10 Floor Joists and ACQ-treated Plate
12-15 Second Truck Loaded with 2X10 Floor Joists and ACQ-treated Plate
 
12-15 Second Truck off Loaded
12-15 Second Truck off Loaded
 
12-15 Unstrapping the Tie Downs for Unloading to Start
12-15 Unstrapping the Tie Downs for Unloading to Start
 
12-15 2X10 Stacks up Awaiting the Floor System Work to Come
12-15 2X10 Stacks up Awaiting the Floor System Work to Come
 
Foundation Work - December 2009 Progress
12-10 First Piling to be Poured in Classroom Building
12-10 First Piling to be Poured in Classroom Building
 
12-9 Storage Building Starting to go up in Lumberyard
12-9 Storage Building Starting to go up in Lumberyard
 
12-8 Forms  off the First Floor Walls of the Dorm Tower
12-8 Forms off the First Floor Walls of the Dorm Tower
 
12-7 Bucket of Mud Flying into Place over the Forms
12-7 Bucket of Mud Flying into Place over the Forms
 
12-6 Foundation Showing Through the Back Fill
12-6 Foundation Showing Through the Back Fill
 
12-5 Scaffolding is up Inside for a Walkway to Pour Mix
12-5 Scaffolding is up Inside for a Walkway to Pour Mix
 
12-4 8M Down the Hole with Little Light
12-4 8M Down the Hole with Little Light
 
12-3 Forms Coming off the West Dorm
12-3 Forms Coming off the West Dorm
 
12-2 GC and Inspectors confirm on Quality and Conformity of the Work to the Plans
12-2 GC and Inspectors confirm on Quality and Conformity of the Work to the Plans
 
12-1 Forms Continue to be Installed
12-1 Forms Continue to be Installed
 
Foundation Work - November 2009 Progress
11-30 Slab Done for the Lumberyard
11-30 Slab Done for the Lumberyard
 
11-29 Working 7M Down the Hole
11-29 Working 7M Down the Hole
 
11-28 Pour has Started again in the Lumberyard
11-28 Pour has Started again in the Lumberyard
 
11-27 Concrete Reinforcement Installed in a Hole
11-27 Concrete Reinforcement Installed in a Hole
 
11-26 View of the Foundation Work Half Way Done
11-26 View of the Foundation Work Half Way Done
 
11-25 Mud Tower Halled up a Plank System to a Road of Planks
11-25 Mud Tower Halled up a Plank System to a Road of Planks
 
11-24 Tools of the Trade Working in the Bottom
11-24 Tools of the Trade Working in the Bottom
 
11-23 Digging in the Piling holes is Close Quarters and Hard Work
11-23 Digging in the Piling holes is Close Quarters and Hard Work
 
11-22 First Bolts are Installed
11-22 First Bolts are Installed
 
11-21 Footing Rebar in Footing Before Being Poured
11-21 Footing Rebar in Footing Before Being Poured
 
11-20 Site Seen from Northwest Corner of Property Showing the Dorm Foundation Work
11-20 Site Seen from Northwest Corner of Property Showing the Dorm Foundation Work
 
11-19 Getting Ready to Pour East Dorm
11-19 Getting Ready to Pour East Dorm
 
11-18 East Dorm Walls are Near Pouring
11-18 East Dorm Walls are Near Pouring
 
11-15  With no Bracing yet the Walls are Amazingly Straight
11-15 With no Bracing yet the Walls are Amazingly Straight
 
11-14 Forms are set to Chaulk Lines
11-14 Forms are set to Chaulk Lines
 
11-12 Site Seen from West Hillside.jpg
11-12 Site Seen from West Hillside.jpg
 
11-11 Looking West Across the East Section of the Dorm
11-11 Looking West Across the East Section of the Dorm
 
11-10 First Forms are Installed for Footings
11-10 First Forms are Installed for Footings
 
11-8 The Sand Layer is Spread over the Contoured Lumber Yard
11-8 The Sand Layer is Spread over the Contoured Lumber Yard
 
11-7 First Walls Get Dug in the Second Half of the Dorm
11-7 First Walls Get Dug in the Second Half of the Dorm
 
11-6 Costruction Manager Reviewing Work Completed for the Day
11-6 Costruction Manager Reviewing Work Completed for the Day
 
11-5 Drilling a Hole and Packing a hole With Explosives
11-5 Drilling a Hole and Packing a hole With Explosives
 
11-3 Chalk Lines Identifying Dorm Footings
11-3 Chalk Lines Identifying Dorm Footings
 
11-2 First Footing is Dug on the Dorm
11-2 First Footing is Dug on the Dorm
 
Foundation 2009 Work - October Progress
10-31 Power Company Setting Poles to the Transformer
10-31 Power Company Setting Poles to the Transformer
 
10-30 Chalked Out Lumberyard Ready
10-30 Chalked Out Lumberyard Ready
 
10-29 Vault for Under the Transformer is Getting its Stucco Coat and Water Proofing.jpg
10-29 Vault for Under the Transformer is Getting its Stucco Coat and Water Proofing.jpg
 
10-25 More Plasting
10-25 More Plasting
 
10-24 Heaved Soils From the Pressures of the Hill Moving Above
10-24 Heaved Soils From the Pressures of the Hill Moving Above
 
10-23 What Was a Foot After the Quake is now Nearly 20 Inches Wide
10-23 What Was a Foot After the Quake is now Nearly 20 Inches Wide
 
10-22 Site Seen From Above an Eastern Cherry Orchard
10-22 Site Seen From Above an Eastern Cherry Orchard
 
10-21 Twenty Feet Back from the Face of the Excavation
10-21 Twenty Feet Back from the Face of the Excavation
 
10-19 Moving Dirt Into the Sports Field
10-19 Moving Dirt Into the Sports Field
 
4-2 Moving Trusses for the Kitchen Roof
4-2 Moving Trusses for the Kitchen Roof
 